Attach the starter strip.
How to lay 3 tab roofing.
However most people prefer the cutout lines to be aligned so they make straight vertical lines.
Install the drip edge over the gable end felt and under the eaves felt.
However make sure that you do not nail into the tar strip.
Video 11 install fascia boards soffit material.
Make sure that the tabs are lining up with the bottom line and that the tabs are facing down.
Roll out and staple down roofing felt in overlapping rows.
Each tab is 12 inches.
Some roofers install shingles so the cutout lines describe a slight angle as you look from the bottom to the top of the roof.
Video 10 install roof sheathing.
Using your staple gun secure the felt to the roof.
Lay a starting row at the bottom of the roof along the edge.
Place nails in the three tab shingles about 3 4 inch 1 8 centimeters above the cutouts near where the tab meets the upper part of the shingle.
Next lay your first full single row of shingles by aligning the shingles on the centerline of the roof.
They will go in the same location as the nails that went in on the first line.
Again use four nails to install the three tab shingles.
Use plenty of staples and work carefully to avoid tearing the paper.
They are designed to be installed with a 5 inch reveal.
How to shingle a shed with 3 tab and architectural shingles.
If you live in an area with inclement weather you should consider using a special ice and water protector.
The tabs should be facing down and aligned with the bottom of the starter line of shingles.
You will once again need 4 nails whenever you are installing the 3 tab shingles.
Three tab shingles are usually 36 inches long.
Video 14 how to install an entrance door.
The first full shingle that you lay will need to be laid along the centerline of your roof.
Some roofers will use 15 pound 6 8 kg roofing paper which is an effective method although the best method is a self sealing membrane with a rain screen.
Video 12 install lp smart side panels part 2.
Many pros shingle in a vertical line up the roof because it s much faster.
Overlap each row at least 3 inches.
Known in the trade as vertical racking or staggering this how to lay shingles method enables the roofer to install a single column of shingles all the way to the peak without the wasted back and forth motion necessary to fill several rows of stair steps.
Video 9 build install soffit ladders.
Overlap each row at least 3 to 4 inches.
Staple this felt down starting at the lowest point of your roof and working upward.